ProjectCodeMeter Reference Traditional Cost Models Report
Report Creation Time 2012-04-05 12:42:00
Software Version Pro v1.24 Licensed to Unregistered Trial

Settings
Analysis Type Normal
Programmer price per hour $93
Quality Guarantee First Release (v1.0) 3-Sigma
Platform Maturity Popular Stable and Documented
Debugging Tools Complete system Step Emulator / VM / ICE
Project Folder e:\sabk\sources\PADUpdaterUnprotected\

COCOMO 81 Basic
Work (Hours) 1295.0
Cost 120433

COCOMO 81 Intermediate
Work (Hours) 1895.3
Cost 176261
Development Mode Organic
Required software reliability (RELY) Normal
Complexity of the product (CPLX) High
Use of software tools (TOOL) Very High

COCOMO II 2000 Nominal
Work (Hours) 1684.4
Cost 156647

COCOMO II 2000 Intermediate
Work (Hours) 1260.4
Cost 117218
Precedentedness (PREC) High
Development Flexibility (FLEX) High
Architecture or Risk Resolution (RESL) Normal
Team Cohesion (TEAM) High
Process Maturity (PMAT) High
Required software reliability (RELY) Normal
Complexity of the product (CPLX) High
Use of software tools (TOOL) Very High
Platform Volatility (PVOL) Low

REVIC 9.2 Nominal
Basic Effort (Hours) 1869.3
Requirements Review Phase (Hours) 224.3
Test and Evaluation Phase (Hours) 411.3
Total Effort (Hours) 2504.9
Total Cost 232952

REVIC 9.2
Basic Effort (Hours) 1784.3
Requirements Review Phase (Hours) 214.1
Test and Evaluation Phase (Hours) 392.5
Total Effort (Hours) 2390.9
Total Cost 222353
Development Mode Organic
Required software reliability (RELY) Normal
Complexity of the product (CPLX) High
Use of software tools (TOOL) Very High